Inground Bollard Installation
1. Locate
Find where the bollards will be installed.
2. Check for Hazards
Always check for hazards such as water pipes, gas lines and underground wiring before digging.
Also check traffic conditions to ensure safety for yourself, pedestrians and vehicles.
3. Drill Recommendations
| Surface | Recommendation |
|---|---|
| Bitumen | Cut bitumen to a square at least bollard width + 100mm, then dig to a depth of at least 600mm |
| Concrete | Core drill with a bit at least bollard width + 100mm, then dig to a depth of at least 400mm |
| Sand / soil | Dig a 350mm × 350mm concrete footing to a depth of at least 600mm |
4. Install Bollard
Place the bollard assembly in the centre of the installation hole.
5. Concrete
Mix and prepare concrete according to instructions, then pour evenly into the site.
6. Inspect
Inspect the bollard to ensure it is level.
7. Time to Cure
Allow 2–3 days minimum for concrete to cure before beginning construction work on the surface.
Moisture and cool temperatures may slow the curing process.
Filling of Bollards
We do not recommend filling bollards with concrete, as a hard impact may cause the bollard to snap at the base.
If filling is required, we recommend sand or loose gravel, which still allows the bollard to bend on impact.
Note:
These recommendations are a guideline only and may not account for site-specific conditions.